|


| |
MINUTES OF THE YEAR END MEETING OF DEC. 27, 2006 OF BOROUGH COUNCIL
The year-end meeting of the Hamburg Borough Council was held this evening at
the Hamburg Municipal Center with President Tammy Wilkinson presiding. The
meeting was opened with Pledge of Allegiance to the Flag and a Prayer.
Members Present Tammy Wilkinson, Martha Bertolet, Dale Schlenker, Roger
Stetzler, Elaine Swavely, Roy Heffner, Jeanette Heckman
Members Absent None
Also Present Lynda G. Albright, Borough Manager, Kim Y. Berger, Recording
Secretary, Solicitor Zubey,
Visitors Chief Michael Painter, Stephen DeLucas - Reading Eagle
A motion was made by Dale Schlenker and seconded by Roy Heffner to
approve the amended agenda.
ROLL CALL: AYES T. Wilkinson, M. Bertolet, J. Heckman, D. Schlenker, R.
Stetzler, R. Heffner,
E. Swavely
NAYES None
COURTESY TO AUDIENCE
NONE
A motion was made by Roy Heffner and seconded by Jeanette Heckman to approve
the minutes of December 11, 2006 meeting as submitted.
ROLL CALL: AYES T. Wilkinson, M. Bertolet, J. Heckman, D. Schlenker, R.
Stetzler, R. Heffner,
E. Swavely
NAYES None
A motion was made by Roger
Stetzler and seconded by Roy Heffner to approve the following reports: Engineers
Report, Civil Service Commission Report and Property Committee.
ROLL CALL: AYES T. Wilkinson, M. Bertolet, J. Heckman, D. Schlenker, R.
Stetzler, R. Heffner,
E. Swavely
NAYES None
ENGINEERS REPORT
December 20, 2006
SANITARY SEWER SYSTEM
SEWAGE TREATMENT PLANT ISSUES
The wastewater treatment plant has again operated better in
the month of November. Systems Design Engineering, Inc., Keith Brobst and plant
staff continues to watch the plant carefully to determine corrective action for
the difficulties encountered in the past.
Systems Design Engineering, Inc. is also working with the
Solicitor on the EPA issues.
WWTP PROJECT
Bids were received for the Wastewater Treatment Plant on
February 17, 2005. The Authority at their February 22, 2006 meeting issued the
"Intent to Award" to:
General/Mechanical Contract DESCCO Design and Construction,
Inc.
Amount of Contract: $5,866,184.00
Change Orders No. 1 $ 7,412.00
$5,873,569.00
Electrical Contract J.B. Electric Corp.
Amount of Contract: $983,469.00
HVAC Contract PSI Pumping Solutions
Amount of Contract: $70,900.00
Contracts were executed and the "Notice to Proceed"
was issued on March 17, 2006 to all contractors. The pre-construction meeting
was held on March 16, 2006. Work is progressing very well. The Contractor is
maintaining the work site in a clean and safe condition.
Work completed this period:
Oxidation Ditch precast complete and tested, mechanical
equipment installed. Handrails being installed
Clarifiers tested and approved. Weirs and mechanical
equipment are being completed.
Pump building and electrical room nearly complete.
Distribution box concrete complete with yard piping and
stop gates
Mechanical yard piping progressing. Complete route from
pump station to the clarifiers is complete. Chlorine Contact and effluent in
progress.
Electrical Contractor working on conduit system, generator
and switchgear installed. Motor Control Center installed and wiring of
equipment progresses.
Backfilling around the clarifiers complete to rough grade
Applications for Payment
DESCCO Design and Construction Application No. 9
(Requisition 237)
Amount $ 525,398.00
Balance on Contract $1,860,314.00
J.B. Electric Corp. Application No. 6 (Requisition 238)
Amount $145,800.00
Balance on Contract $458,949.00
Systems Design Engineering, Inc. assists the Solicitor on
financing issues as required. The closing of the Commonwealth Financing
Authority loan occurred on Friday September 15, 2006.
Systems Design Engineering, Inc. has submitted payment
applications for the complete grant amount and the first draw for the loan to
provide continued cash flow for the remainder of the project. The first draw
on the loan of approximately $2.5 million was received. The full grant amount
from PENNWORKS was received in the amount of 687,250.00. The Authority has
received confirmation of the DCED allocation of the Berks County grant in the
amount of $130,000 per year for 10 years ($1,300,000 total). The second draw
on the PENNWORKS loan is being worked on.
PUMP STATION PROJECT
Bids were received for the Pine Street Pump Station on
December 16, 2005. The Authority has issued the "Intent to Award"
to:
General/Mechanical Contract Pikeland Construction, Inc
Amount of Contract: $585,000.00
Change Orders $ 5,200.00
$590,200.00
Electrical Contract Pagoda Electrical, Inc.
Amount of Contract: $206,000.00
Change Order $ 178.64
$206,178.64
The Award and Notice to Proceed was issued on January 20,
2006.
Work this period included:
The project is substantially complete. Punch list items are
being completed. Project closeout is in progress.
Evaluation of adding air release ports to the pumps are
progressing. Additional tests to evaluate a water flush are also being
investigated.
Applications for Payment
Pikeland Construction, Inc.
Amount $ 0.00
Balance on Contract $ 66,465.00
Pagoda Electrical
Amount $ 0.00
Balance on Contract $ 11,733.93
CORRECTIVE ACTION PLAN and I/I WORK
Systems Design Engineering, Inc. is proceeding with review
of repairs of the collection system as determined by the past televising
contract.
WISSAHICKON WATER (no change)
Wissahickon started production. Systems Design Engineering,
Inc. and Keith inspected the facility and have instructed Wissahickon on
procedures and some operational details.
PROJECTS
Bids for the force main upgrade of the Edenburg Pump
Station was received September 6, 2006. Intent to award, Award and Notice to
Proceed was given at the September 6, 2006 meeting. Contracts have been
executed.
The force main installation is nearly complete. The final
tie-in is scheduled within the next several days.
WATER SYSTEM
WATER PRODUCTION
The impoundment dam has is full. The plant operator restarted the filter
plant but elected to shut it down due to difficulties with operation. Most
water for this report period was produced from the wells. Proposals are being
solicited for replacement of the control system of the filter plant. We have
contacted Optimum Control Corp. (OCC), a Reading based firm to quote the
project. OCC programs water filter plants for Infilco. A budget price on
rebuilding the control system will be presented.
REQUISITIONS
Requisition 237 DESCCO Design and Construction $525,398.00
Requisition 238 J.B. Electric Corp. $145,800.00
Requisition 239 Systems Design Engineering, Inc. $
18,222.10
Requisition 240 L/B Water Service $ 1,560.00
Requisition 309 L/B Water Service $ 4,062.64
Requisition 310 Systems Design Engineering, Inc. $ 475.55
TO: BOROUGH COUNCIL, BOROUGH OF HAMBURG
FROM: THE HAMBURG CIVIL SERVICE COMMISSION
2006 YEAR END REPORT
The 2006 calendar year brought little changes to the Hamburg Civil Service
Commission.
The rules and regulations were updated whereby changing qualifications for
promotions and some other word changes.
Minutes of the meetings are on file in the Borough Office. See Kim Y. Berger,
Office Manager/Recording Secretary to make arrangements for further review of
such.
Respectfully submitted,
Hettie L. Riegel/s/
Secretary, Civil Service Commission
PROPERTY COMMITTEE DECEMBER 19, 2006
MUNICIPAL CENTER 3:30PM
ATTENDING: Lynda Albright, Elaine Swavely, Tammy Wilkinson, Roger Stetzler,
Roy Heffner & Dale Schlenker
VISITORS: Deena Kershner & Mike Painter
Deena Kershner representing Our Town Foundation presented the opportunity
for the next round of Streetscape monies and asked the committee if we were
willing to support the issue. We all agree she should "go for it"
and the Borough would support her in any way we could. She also indicated
matching grants monies for previously purchased products and labor could be
used. We encouraged her to pursue this and the committee indicated the
support of the Borough in using these matching funds. Other issues such as
storing slate and a spare new light standard were discussed and approved.
All committees were urged to give their "WISH LISTS" of needed
projects to Tammy and Deena so a coordinated effort can move forward
inquiring on available grants.
Sylvandale Forrest has presented additional areas available for improved
land management; the Property Committee recommended the project go forward
as presented.
Lynda was instructed to RE-CONTACT First Energy about the dangerous poles
within the Streetscape construction area and ascertains why they did not
return a comment. The legislators will also be contacted on this issue.
Wade will be contacted to meet with the Property Committee in January
regarding the pool Bath houses and the need to install handicap areas
The newly installed Garage door at the "Frey Building" on
Franklin St. has already been damaged. Rumble strips will be installed (if
possible) to defer further damage to the door and to the pool storage
building as well.
THANK YOU Rotary Club for volunteering to pick up Christmas trees January
6, 2006.
After review by the Police Department, signs will be erected at the
Hamburg Park/Pool showing the new rules.
A request was made to have a building erected on the lot purchased by the
Borough last year at Front & State. It was decided to wait until the
Hamburg Planning Commission, Schuylkill River Heritage and the Berks County
Redevelopment Commission finalize a plan for the area and present to Borough
Council for approval.
CHAIRMAN OF PROPERTY DALE R. SCHLENKER
OLD BUSINESS
On the recommendation of the Finance Committee, a motion was made by Martha
Bertolet and seconded by Roger Stetzler to approve the 2007 General Budget in
the amount of $3,105,350
ROLL CALL: AYES T. Wilkinson, M. Bertolet, J. Heckman, D. Schlenker, R.
Stetzler, R. Heffner,
E. Swavely
NAYES None
On the recommendation of the Borough Manager, a motion was made by Elaine
Swavely and seconded by Dale Schlenker to adopt Ordinance #745-06,
amending the EMST tax.
ROLL CALL: AYES T. Wilkinson, M. Bertolet, J. Heckman, D. Schlenker, R.
Stetzler, R. Heffner,
E. Swavely
NAYES None
On the recommendation of the Finance Committee, a motion was made by Roger
Stetzler and seconded by Roy Heffner to adopt Ordinance #746-06, establishing
the tax rate of 5.25 mills for general operations and .25 for fire company
operations for year 2007.
ROLL CALL: AYES T. Wilkinson, M. Bertolet, J. Heckman, D. Schlenker, R.
Stetzler, R. Heffner,
E. Swavely
NAYES None
A motion was made by Dale Schlenker and seconded by Martha Bertolet
to make the following appointments
for 2007.
ROLL CALL: AYES T. Wilkinson, M. Bertolet, J. Heckman, D. Schlenker, R.
Stetzler, R. Heffner,
E. Swavely
NAYES None
Earl Fox Plumbing Inspector
Lynda Albright EMST Collector/Asst. Bldg./Zoning and Asst.
Code Enforcement Officer
John Leonforte Bldg./Zoning Officer/Code Enforcement Officer
Systems Design Engineers Consulting Engineer
Great Valley Consultants Planning Engineer
Berks Envirotech SEO
Union Fire Co. #1 of Hamburg official Fire Company
Hamburg Legion Ambulance official ambulance service
Masano Bradley - Solicitor
On the recommendation of the Borough Manager, a motion was made by Roy
Heffner and seconded by Roger Stetzler to take action setting the rate for
police pension payroll
deduction at 4-1/4% for 2007.
ROLL CALL: AYES T. Wilkinson, M. Bertolet, J. Heckman, D. Schlenker, R.
Stetzler, R. Heffner,
E. Swavely
NAYES None
On the recommendation of the Personnel Committee, a motion was made by Dale
Schlenker and seconded by Roger Stetzler to reappoint Heather Breininger
to another 4-year term on the Planning Commission, term ending 12/31/10.
ROLL CALL: AYES T. Wilkinson, M. Bertolet, J. Heckman, D. Schlenker, R.
Stetzler, R. Heffner,
E. Swavely
NAYES None
NEW BUSINESS
A motion was made by Roy Heffner and seconded by Roger Stetzler authorizing
the Borough Manager to make budgetary transfers as necessary (within each
organization area of the budget).
ROLL CALL: AYES T. Wilkinson, M. Bertolet, J. Heckman, D. Schlenker, R.
Stetzler, R. Heffner,
E. Swavely
NAYES None
On the recommendation of the Property Committee, a motion was made by Dale
Schlenker and seconded by Roger Stetzler authorizing Sylvandale Forrest
to move forward on the project regarding improved land management.
ROLL CALL: AYES T. Wilkinson, M. Bertolet, J. Heckman, D. Schlenker, R.
Stetzler, R. Heffner,
E. Swavely
NAYES None
SOLICITORS REPORT
Nothing to report
A motion was made by Dale Schlenker and seconded by Roy Heffner to
approve payment of invoices totaling $83,187.32
ROLL CALL: AYES T. Wilkinson, M. Bertolet, J. Heckman, D. Schlenker, R.
Stetzler, R. Heffner,
E. Swavely
NAYES None
(T. Wilkinson abstained from the bill payable to herself due to direct
income)
LIST OF BILLS
BLUE MT. COMPUTER 1,475.00
CAPTAIN CLOG 450.00
LAURA CINTRON, COURT REPORTER 235.20
EHRLICH 140.00
GALLS 104.96
HAMBURG MUNICIPAL AUTHORITY 119.29
ML CONSTRUCTION 1,783.00
JP MASCARO 11,160.00
MCTISH, KUNKEL & ASSC. 8,674.00
MEIT 202.50
NATL. ELEVATOR INSPECTION 60.00
PMHIC 25,415.12
PA DEPT. OF LABOR & INDUSTRY 36.00
PATRIOT COLLISION CENTER 2,141.14
RANDYS CARPET 210.00
RARITAN VALLEY DISPOSAL 19,346.79
REPPERTS 421.52
ES SAVAGE 138.78
SUSTAINABLE ENERGY FUND 212.69
SYSTEMS DESIGN 905.47
UNIFIRST 268.84
TAMMY WILKINSON 37.02
DUDA ACTUARIAL CONSULTING 2,150.00
UNION FIRE CO. #1 OF HAMBURG 7,500.00
TOTAL FOR APPROVAL $83,187.32
UPCOMING MEETINGS/INFORMATION
JANUARY 1, 2007 HAPPY NEW YEAR! (OFFICE CLOSED)
January 2, 2007 7 PM - RECREATION BOARD
January 8, 2007 COUNCIL MEETING
JANUARY 6, 2007 ROTARY PICKING UP XMAS TREES FROM 8 A.M. TO 12 NOONTREES
TO BE PLACED AT SAME LOCATION AS TRASH/RECYCLING
There being no further business, the meeting was adjourned at 7:42 p.m. on
motion of Dale Schlenker and seconded by Roger Stetzler.
ATTEST:
Kim Y. Berger
Recording Secretary/Office Manager
|