DEC. 20, 2006

Home
Up

MINUTES OF THE DECEMBER 20, 2006 MEETING OF THE AUTHORITY

The meeting of the Hamburg Municipal Authority was held this evening at the Hamburg Municipal Center with Chairman Steve Smith presiding. The meeting started at 7:00 p.m.

Members Present - Stephen A. Smith, David A. Fink, Stanley E. Dietrich, Roger G. Kuhns, Stephen H. Blefgen

Members Absent - Judy E. Romig

Also Present – Gregory T. Unger-SDE, Charles F. Fitzpatrick-Solicitor, Keith L. Brobst- Superintendent, Lynda G. Albright-Borough Manager, Denise L. Clare-

Secretary

A motion was made by Stan Dietrich and seconded by Roger Kuhns to approve the November minutes as written and presented.

ROLL CALL: Ayes- Smith, Fink, Dietrich, Kuhns, Blefgen

Nayes- None

VISITORS

None

The Trustee Treasurer’s, Administrative Treasurer’s and Sewer B,R, & I reports were reviewed.

ACCT. # Account Name Bal.-Oct.06 Credits Debits Bal.-Nov.06

1576025802 Water-1995 Settlement Fund $ 0.00 $ 0.00

1576025820 Water-1995 Revenue Fund $ 0.00 $ 0.00

1576025839 Water-1995 Debt Service $ 1,045.26 $111,927.45 $112,972.71

1576025848 Water-1995 Debt Ser. Res. Fund $232,943.01 $ 16,104.38 ($5,051.76) $243,995.63

1576025857 Water-1995 B, R, & I $687,218.55 $ 2,789.24 ($30,332.28 ) $659,675.51

1576025866 Water-1995 Rebate Fund $ 0.00 $ 0.00

OPERATING WATER/SEWER ACCOUNT ACTIVITY

November 1, 2006 to November 30, 2006

Water Revenue Account – Balance on November 1, 2006 $ 253,923.12

Water Sales/Penalties $ 58,989.32

Water Tap-In Fee $ 3,000.00

Cert Fees, Constable Fees, Final Fees $ 492.50

Interest $ 21,480.66

Miscellaneous $ 171.75 $ 84,134.23

$ 338,057.35

Less Paid Out $ ( 28,533.54)

Balance in Treasury – November 30, 2006 $ 309,523.81

__________________________________________________________________________________________________________

Wissahickon Water Account – Balance on November 1, 2006 $ 2,018.42

Fire hydrant fees/penalties $

Interest $ 7.63

$ 7.63

$ 2,026.05

Less Paid Out $ ( 0.00)

Balance In Treasury – November 30, 2006 $ 2,026.05

__________________________________________________________________________________________________________

Fire Hydrant Account – Balance on November 1, 2006 $ 166,342.90

Fire hydrant fees/penalties $ 2,241.28

Interest $ 631.95

$ 2,873.23

$ 169,216.13

Less Paid Out $ (112.80)

Balance In Treasury – November 30, 2006 $ 169,103.33

__________________________________________________________________________________________________________

Sewer Revenue Account – Balance on November 1, 2006 $ 435,982.89

Sewer Rentals/Penalties $ 63,541.95

WTMA Rentals/Penalties $ 7,377.68

Sewer Tap-In Fee $ 3,000.00

Interest $ 1,911.49

$ 75,831.12

$ 511,814.01

Less Paid Out $ (62,138.27)

Balance in Treasury – November 30, 2006 $ 449,675.74

BOROUGH TREASURER

SEWER BR & I ACCOUNT

AUTHORITY MEETING DECEMBER 20, 2006

 

CHECKING ACCOUNT - BALANCE IN CHECKING 11/1/06 $ 192,430.21

INTEREST $ 521.93

TOTAL RECEIPTS FOR THE MONTH OF NOVEMBER $ 192,952.14

LESS PAID OUT $ (0.00)

BALANCE IN CHECKING 11/30/06 $ 192,952.14

 

Stan Dietrich asked why the Sewer B,R, & I account has less interest than the fire hydrant account when that balance is larger. The Secretary suggested that a different bank would provide different interest rates. Lynda Albright stated that she was not sure. Stan Dietrich asked if this could be checked into. Lynda Albright will ask and get information. Lynda Albright found an error on the report and will check on this as well.

Greg Unger will look at the M & T statements to see if he can figure them out.

A motion was made by Stan Dietrich and seconded by Dave Fink to accept the Trustee Treasurer’s, Administrative Treasurer’s and Sewer B,R, & I reports as written.

ROLL CALL: Ayes- Smith, Fink, Dietrich, Kuhns, Blefgen

Nayes- None

HAMBURG MUNICIPAL AUTHORITY
ENGINEER’S REPORT
December 20, 2006

SANITARY SEWER SYSTEM

SEWAGE TREATMENT PLANT ISSUES

The wastewater treatment plant has again operated better in the month of November. Systems Design Engineering, Inc., Keith Brobst and plant staff continues to watch the plant carefully to determine corrective action for the difficulties encountered in the past.

Systems Design Engineering, Inc. is also working with the Solicitor on the EPA issues.

WWTP PROJECT

Bids were received for the Wastewater Treatment Plant on February 17, 2005. The Authority at their February 22, 2006 meeting issued the "Intent to Award" to:

General/Mechanical Contract DESCCO Design and Construction, Inc.

Amount of Contract: $5,866,184.00

Change Orders No. 1 $ 7,412.00

$5,873,569.00

 

Electrical Contract J.B. Electric Corp.

Amount of Contract: $983,469.00

 

HVAC Contract PSI Pumping Solutions

Amount of Contract: $70,900.00

 

Contracts were executed and the "Notice to Proceed" was issued on March 17, 2006 to all contractors. The pre-construction meeting was held on March 16, 2006. Work is progressing very well. The Contractor is maintaining the work site in a clean and safe condition.

Work completed this period:

Oxidation Ditch precast complete and tested, mechanical equipment installed.

Handrails being installed.

Clarifiers tested and approved. Weirs and mechanical equipment are being

completed.

Pump building and electrical room nearly complete.

Distribution box concrete complete with yard piping and stop gates.

Mechanical yard piping progressing. Complete route from pump station to the clarifiers is complete. Chlorine Contact and effluent in progress.

Electrical Contractor working on conduit system, generator and switchgear

installed. Motor Control Center installed and wiring of equipment progresses.

Backfilling around the clarifiers complete to rough grade.

Applications for Payment

 

DESCCO Design and Construction Application No. 9 (Requisition 237)

Amount $525,398.00

Balance on Contract $1,860,314.00

 

J.B. Electric Corp. Application No. 6 (Requisition 238)

Amount $145,800.00

Balance on Contract $458,949.00

Systems Design Engineering, Inc. assists the Solicitor on financing issues as required. The closing of the Commonwealth Financing Authority loan occurred on Friday, September 15, 2006.

Systems Design Engineering, Inc. has submitted payment applications for the complete grant amount and the first draw for the loan to provide continued cash flow for the remainder of the project. The first draw on the loan of approximately $2.5 million was received. The full grant amount from PENNWORKS was received in the amount of $687,250.00. The Authority has received confirmation of the DCED allocation of the Berks County grant in the amount of $130,000 per year for 1-0 years ($1,300,000 total). The second draw on the PENNWORKS loan is being worked on.

PUMP STATION PROJECT

Bids were received for the Pine Street Pump Station on December 16, 2005. The Authority has issued the "Intent to Award" to:

General/Mechanical Contract Pikeland Construction, Inc

Amount of Contract: $585,000.00

Change Orders $ 5,200.00

$590,200.00

 

Electrical Contract Pagoda Electrical, Inc.

Amount of Contract: $206,000.00

Change Order $ 178.64

$206,178.64

The Award and Notice to Proceed was issued on January 20, 2006.

Work this period included:

The project is substantially complete. Punch list items are being completed. Project closeout is in progress.

Evaluation of adding air release ports to the pumps are progressing. Additional tests to evaluate a water flush are also being investigated.

Applications for Payment

Pikeland Construction, Inc.

Amount $ 0.00

Balance on Contract $66,465.00

Pagoda Electrical

Amount $ 0.00

Balance on Contract $11,733.93

CORRECTIVE ACTION PLAN and I/I WORK

Systems Design Engineering, Inc. is proceeding with review of repairs of the collection system as determined by the past televising contract.

WISSAHICKON WATER (no change)

Wissahickon started production. Systems Design Engineering, Inc. and Keith inspected the facility and have instructed Wissahickon on procedures and some operational details.

PROJECTS

Bids for the force main upgrade of the Edenburg Pump Station was received September 6, 2006. Intent to award, Award and Notice to Proceed was given at the September 6, 2006 meeting. Contracts have been executed.

The force main installation is nearly complete. The final tie-in is scheduled within the next several days.

WATER SYSTEM

WATER PRODUCTION

The impoundment dam has is full. The plant operator has restarted the filter plant but elected to shut it down due to difficulties with operation. Most water for this report period was produced from the wells. Proposals are being solicited for replacement of the control system of the filter plant. We have contacted Optimum Control Corp. (OCC), a Reading based firm to quote the project. OCC programs water filter plants for Infilco. A budget price on rebuilding the control system will be presented.

REQUISITIONS

Requisition 237 DESCCO Design and Construction $525,398.00

Requisition 238 J.B. Electric Corp. $145,800.00

Requisition 239 Systems Design Engineering, Inc. $ 18,222.10

Requisition 240 L/B Water Service $ 1,560.00

Requisition 309 L/B Water Service $ 4,062.64

Requisition 310 Systems Design Engineering, Inc. $ 475.55

Greg Unger reported that the Pine Street Pump Station project was 98% complete. Contractors are currently working on punch list items.

Fiberglass door issues on warm days

Relay in the control system was replaced. Training for this is needed.

Exhaust fan ventilation issue, fan may have to be replaced.

Greg Unger will get Steve Blefgen to do a walk thru of the Pine Street Pump Station. This will be scheduled for December 26 at 8:00 a.m. if any other members would like to attend.

Greg Unger reported that there were no requisitions for the Pine Street Pump Station this month but there is a change order. It is change order #2 for Pagoda in the amount of $2,161.08. It is for a wire block cooler on the generator, to relocate the blower connect and feed and additional power wiring for the flow meter.

Greg Unger stated that there were 2 requisitions for the WWTP and 1 change order. Change order #1 for J.B. Electric in the amount of $2,791.11 to change out the 8 disconnect switches from 3R’s to 4X’s.

Greg Unger reported that grant money that is to be received every year for 10 years will be $130,000/year. Originally, Greg Unger thought this would only be $93,000/year. Charles Fitzpatrick asked where this money was coming from. Greg Unger stated that it was from Berks County DCED, BCIDA and IFIP. Greg Unger read the following letter regarding this:

Thomas McKeon

Executive Director

Berks County Industrial Development Authority

Berks County Services Center

633 Court Street, 14th Floor

Reading, PA 19601

RE: Infrastructure and Facilities Improvement Program

Grant: $9,300.00

Cabela’s Retail Inc.

C000016860

Mr. McKeon:

I am writing regarding the $930,000 Infrastructure and Facilities Improvement Program (IFIP) grant awarded to Berks County Industrial Development Authority (BCIDA) on December 2, 2006. It is the intention of the Department of Community and Economic Development (DCED) that $800,000 of the award be used by BCIDA to pay annual debt service on eligible infrastructure improvements at Cabela’s Retail Inc. facility and $130,000 to be utilized by the Hamburg Municipal Authority to cover debt ser vice on the sewer improvements servicing the same retail facility.

If you have any questions, please do not hesitate to contact me.

Sincerely,

/s/ Scott D. Dunkelberger

Director, Center for Business Financing

Greg Unger handed out spreadsheets showing the sewer amortization schedule. 56.07% is Tilden Township’s share and 43.93% is the Authority’s share. Greg Unger went over the spreadsheet. He would like this to be submitted to Tilden Township to get a cash flow started. This way they can see how much they are responsible for. Tilden Township just submitted the project to DEP for approval. Tilden Township has not gone for PennWorks money yet (this could take 6 months). Tilden Township is only breaking ground in spring of 2008 and will take a year to complete. There will be no new connections until 2009.

Edenburg Force Main-Greg Unger reported that this project is 95% complete. The tie in will be done on December 26. This will take 2-3 hours.

Greg Unger reported that the Forino project near Ridge Lawn will not be happening so therefore Forino will not be helping to upgrade the Ridge Lawn Pump Station. The Authority will have to undertake this project. There are 2 options:

$2,500 + $2,000 to rebuild into the panel

$6,500 + $1,000 to install all new

Greg Unger recommended the second option and stated that this can be done with telephone bids. It was decided to go with option #2.

Greg Unger has escrow release #2 for Greth Development Group for the Towns at Kaercher in the amount of $46,393.84. This needs to be approved by the Authority.

Greg Unger reported that the water filtration plant is currently offline. There are still control issues. A quote has been received from OCC to rebuild the control panel at a cost of $85,500. OCC is a local company. This project will need to be bid.

A motion was made by Roger Kuhns and seconded by Dave Fink to authorize Systems Design Engineering, Inc. to bid the upgrade of the water filtration plant control system.

ROLL CALL: Ayes- Smith, Fink, Dietrich, Kuhns, Blefgen

Nayes- None

Stan Dietrich asked about the I/I work. Greg Unger stated that he is working on bid specs. There is a large list of things to do. This will take 1-2 years to complete and will be done in sections.

SOLICITOR’S REPORT

Charles Fitzpatrick reported that EPA forwarded a letter to the mediator requiring the original $90,000 fine. Negotiations have been ongoing and the tables have been reviewed to come up with a figure of $31,000. The tables were again looked at and $41,000 was derived. This was forwarded to EPA and the judge. EPA will not take less than the $51,000 that was the difference between $71,000 EPA fine and the $31,000 the Authority came up with. EPA has now come up with a fine of $157,500, which included fines for 2006 violations. If this goes to court it will cost more with legal fees and court costs. The judge has recommended accepting the $51,000 fine. The judge also suggested adding in a supplemental environment project to take the penalty to help in the municipality. $20,000 of the $51,000 could be used for the project. Charles Fitzpatrick suggested using it for the I/I work. EPA would get the remainder of the money. This is the recommendation of the solicitor and will include any violations for 2006. Other projects the money could be used

for would be the water filtration plant upgrade or storm sewers. Greg Unger suggested listing the projects in order of preference.

A motion was made by Dave Fink and seconded by Steve Blefgen to approve Charles Fitzpatrick’s recommendation to settle with EPA for $51,000 with the Supplemental Environment Project being a part of it and the 2006 violations added in.

ROLL CALL: Ayes- Smith, Fink, Dietrich, Kuhns, Blefgen

Nayes- None

Charles Fitzpatrick reported about 232 Pine Street and the correspondence between the Authority and the Seaman’s. A response was received from the Seaman’s on November 23. Parts of the letter were read by Charles Fitzpatrick. Lynda Albright received a letter on November 30 from Arlene Seaman. The following letter was read by Lynda Albright:

Lynda Albright

Borough Manager

c/o Hamburg Municipal Authority

51 North 3rd Street

Hamburg, PA 19526

RE: Your letter of November 24, 2006

Please be advised of the following

The boro of Hamburg has the right of access to the site or sites of proposed work at the residence, 232 Pine Street, Hamburg, Pa.

Any property damage is already covered by the law.

Please forward any questions or communications to Mr. Paul R. Ober, Esquire, 607 South 4th Street, Hamburg, Pa. 610-562-5879.

Thanks you for your attention to these matters.

Sincerely yours,

/s/ Arlene R. Seaman

A letter was also received from Evelyn Seaman regarding their heating system.

BOROUGH MANAGER’S REPORT

A letter was received from Jean Epting requesting w/s relief for a leak in her meter pit. Ms. Epting does not have access to the pit and would not have known about the leak had it not been for the meter reader reading the meter. The crew has fixed the leak. The bill will be averaged based on previous usage.

The water and sewer budgets for 2007 were sent with the packets to review prior to the meeting. The budgets balanced without rate increases.

A motion was made by Steve Blefgen and seconded by Stan Dietrich to approve both the water and sewer budgets as presented.

ROLL CALL: Ayes- Smith, Fink, Dietrich, Kuhns, Blefgen

Nayes- None

Lynda Albright stated that the first requisition to reimburse the money to the sewer account from M & T needs approval.

CORRESPONDENCE LIST

CORRESPONDENCE NOTES RECEIVED FROM NOVEMBER 16 TO DECEMBER 20, 2006

Copy of letter from SDE to Authority dated November 15, 2006 regarding reduction of the Letter of Credit by Greth Development for the Towns at Kaercher Creek in the amount of $45,501.34.

Copy of letter from SDE to PA DCED dated November 16, 2006 regarding the Penn Works Grant Forms.

Copy of letter from Barley Snyder to U.S. EPA dated November 22, 2006 regarding proposed settlement of sewer violation fine.

Letter to Authority from Comptroller’s Office of the Commonwealth dated November 30, 2006 relative to the Penn Works loan payments (information has been forwarded to the trustee).

Letters from Evelyn and Arlene Seaman to the Borough Manager dated November 30, 2006 relative to the letter sent by Solicitor Fitzpatrick on meter readings and meter replacement at their property on Pine Street.

Letter to the Authority dated December 8, 2006 from Jean Epting regarding a request for relief of water and sewer charges due to a leaky meter in meter pit.

Copy of letter to Tom McKeon of the Berks County Ind. Dev. Authority from PA DCED, dated December 11, 2006, with copy to the Authority advising that the Authority will be receiving $130,000 per year for ten years to offset debt payments for the upgrade and expansion of the sewer plant and pumping station under an Infrastructure and Facilities Improvement Program.

Copy of letter from EPA to EPA dated December 12, 2006, copy to Charles Haws, Esq. Of Barley Snyder relative to the proposed settlement of the sewer violation fine.

SUPERINTENDENT’S REPORT

Water/Wastewater Superintendent’s Report November 2006

Water

Most water for the month was from the surface source. The weekend of the 18th and 19th the plant got a mind of its own and caused significant problems. Signaling from the PLC to the pre-filter soda ash pump became inconsistent and cause turbidity to rise. We worked with it for several days until it became apparent that the filters were unreliable. We will be on well water for the foreseeable future.

The engineer, Tony and I met with a representative of OCC, a company specializing in controls and are waiting for a proposal to replace the control system at the water plant.

The new chlorine booster pumps should be installed very soon. Kohl Bros. have temporarily installed a "loaner" to keep us running till the permanent installation can be done.

The afternoon before Thanksgiving we had a water main break on Walnut Street in the area of Exide. In the process of closing valves to locate this leak another developed at the other end of the block. While the Borough Crew fixed one leak we had a contractor repair the other. The second leak was significant and did some damage to the street. Homes were without water for about 8 hours. Happy Thanksgiving!

Wastewater

Construction is proceeding on schedule and we expect to flow through the oxidation dirt h and new clarifiers by year end.

There have been a few issues regarding the stability of the catwalks on the clarifiers and US Filter along with DESCCO are working to resolve the problem.

On November 9th we noticed a solvent like odor from the primary clarifier however there was no other evidence of a spill at that time. Later that evening Robbie told me he had heard there was a fuel spill at that time on State Street and I went to the Wastewater Treatment Plant to find the primary clarifiers covered with a film of fuel oil. This resulted in an almost total kill of the biomass. We were able to remain in permit compliance and bring the biomass back but we had a nervous couple of days.

A week later extremely heavy rain flooded the Pine Street Pumping Station. This time we were able to avoid a by-pass and treated everything that came down the pipe. The backup into the station, however indicated we still have considerable work to do in the collection system.

Finally, I am happy to report there were no exceptions to the November DMR.

Keith Brobst reported that there was a water leak on November 19. Pictures of the broken pipe were passed around. The leak was on Walnut Street behind Exide. Keith Brobst suggested using the fire hydrant funds to update the mains. Keith Brobst recommended the area around Exide on Walnut Street and a 2" galvanized pipe in Edenburg as water main work to do.

Stan Dietrich asked about the oil leak. Keith Brobst stated that most of the biomass died but some were brought back to health. There was an accident in the tank and a hose left loose.

BILLS & REQUISITIONS

Roger Kuhns asked about the Met-Ed bill, are the numbers reversed? Keith Brobst stated that they were not. He explained that when Met-Ed comes to read the meter the gate is closed and they are unable to get to the meter so the bills have been estimated. Met-Ed has been made aware of this and will be calling prior to coming so they can be left in to read the meter.

Stan Dietrich asked what an ejector body was. Keith Brobst stated that it is part of the chlorinator that puts the chlorine in the water.

Stan Dietrich asked if 1 or 2 tires were purchased. Keith Brobst stated it was 2.

Stan Dietrich asked about the $1,800 bill for the water heater. How big is it? Keith Brobst stated it was 60 gallons and that there were other related items (copper, PRV, etc.) on the bill as well.

A motion was made by Stan Dietrich and seconded by Roger Kuhns to pay the bills as presented.

ROLL CALL: Ayes- Smith, Fink, Dietrich, Kuhns, Blefgen

Nayes- None

HAMBURG MUNICIPAL AUTHORITY

BILLS TO BE PAID

DECEMBER 20, 2006

AT & T s-quarterly phone lease $ 14.55

AT & T w-monthly long distance 61.06

Barley/Snyder s-October legal services 2,377.94

Barley/Snyder w-89.25-s-2074.85 2,160.00

Berks Products Corp w-supplies 332.76

Buck Transport, Inc. w-delivery stone 120.00

DelRosario, Roy C. w-constable fees 195.51

DelRosario, Roy C. w-constable fees 102.23

Ehrlich Co. Inc. s-monthly pest service 39.00

Environmental Resource Association s-supplies 128.53

Ernst Cabinet Works s-plumbing fixtures 41.83

Exeter Supply Co., Inc. w-1210.78-s-929.48 2,140.26

Four Star Electronics w-248.00-s-1584.00 1,832.00

Hamburg Municipal Authority s-utility bills 328.57

Hach Company w-chlorine reagent 119.03

Kantner’s Tire Service s-tire repair 12.00

Kershner, Mike w-1073.65-s-245.40 1,319.05

Kershner, Mike w-water plant repairs 247.75

L/B Water Service Inc. w-meter parts 400.50

Liquid Motion Inc. w-120.00-s-4236.00 4,356.00

J.P. Mascaro & Sons s-sludge removal 1,643.72

Met-Ed w-1371.49-s-8056.33 9,427.82

Mountain View Supply s-supplies 80.52

Mountain View Supply s-supplies 2.28

PA One Call System, Inc. w-8.50-s-8.50 17.00

PPL Gas Utilities s-utility bills 429.56

Penn Fuel Propane w-propane 407.68

Penn Fuel Propane w-propane 597.17

Penn Pride, Inc. w-44.50-s-133.30 177.80

Pyrz Water Supply Company, Inc. w-ejector body 639.00

Quill Corporation s-office supplies 123.25

Reider, MJ Associates s-laboratory services 1,252.00

Reider, MJ Associates w-laboratory services 437.00

Schaeffer, Richard M. s-replace water heater 1,858.40

Schlouch Inc. w-emergency water main repair 1,941.22

Systems Design Engineering, Inc. w-4821.02-s-5584.24 10,405.26

United Parcel Service s-charges to return probe 25.23

USA Bluebook s-repair parts 327.62

Univar USA Inc. w-stern pac 2,360.31

Verizon w-107.90-s-230.99 338.89

Water Works Operators’ Assn. w-2007 memberships 60.00

Werley, Francis L. Inc. s-fuel for generator 3,354.16

Werley, Francis L. Inc. s-tire repair 12.00

TOTAL $51,138.19

Bills To Be Paid total water $ 17,138.19

total sewer $ 34,700.59

Bills Paid During The Month

total water $ 20,961.90

total sewer $ 34,449.28

Grand Total For Approval

total water $ 38,100.09

total sewer $ 69,149.87

$107,249.96

PREPAID INVOICE LIST

Yoder’s Heating s-replace furnace $ 3,362.82

M & T Investment sewer note fee 1,000.00

Clare, David A. w-meter reader 196.30

Miller, Ann M. w-meter reader 177.45

Sonon, Craig A. w-meter reader 122.20 Borough of Hamburg w-20337.82-s-29948.82 50,286.64

Petty Cash s-supplies 9.50

Postmaster of Hamburg w-128.13-s-128.14 256.27

TOTAL $55,411.18

Requisition #237 Sewer B,R, & I $525,398.00

DESCCO Design & Construction

WWTP-Contract A

Requisition #238 Sewer B,R, & I $145,800.00

J.B. Electric

WWTP-Contract B

Requisition #239 Sewer B,R, & I $ 18,222.10

Systems Design Engineering, Inc.

WWTP Engineering

Requisition #240 Sewer B,R, & I $ 1,560.00

L/B Water Service

Lifting Device

Requisition #309 Water B,R, & I $ 4,062.64

L/B Water Service

Water Meters

Requisition #310 Water B,R, & I $ 475.55

Systems Design Engineering, Inc.

Engineering Design

A motion was made by Steve Blefgen and seconded by Stan Dietrich to pay change order #2 for Pagoda, change order #1 for J.B. Electric, to reduce the letter of credit for the Towns at Kaercher and the requisitions as presented.

ROLL CALL: Ayes- Smith, Fink, Dietrich, Kuhns, Blefgen

Nayes- None

Lynda Albright had a requisition to transfer the money from M & T to the sewer account in the amount of $34,700.59.

A motion was made by Steve Blefgen and seconded by Roger Kuhns to approve the requisition as presented.

ROLL CALL: Ayes- Smith, Fink, Dietrich, Kuhns, Blefgen

Nayes- None

NEW BUSINESS

None

OLD BUSINESS

None

There being no further business, a motion was made by Stan Dietrich to adjourn the meeting at 8:55 p.m.

Attest:

Denise L. Clare, Recording Secretary