MARCH 21, 2007

Home
Up

MINUTES FROM MARCH 21, 2007 AUTHORITY MEETING

The meeting of the Hamburg Municipal Authority was held this evening at the Hamburg Municipal Center with Chairman Steve Smith presiding. The meeting started at 7:05 p.m.

Members Present - Stephen A. Smith, David A. Fink, Stanley E. Dietrich, Stephen H. Blefgen

Members Absent - Roger G. Kuhns, Judy E. Romig

Also Present – Gregory T. Unger-SDE, Charles Haws-Solicitor, Keith L. Brobst-Superintendent, Lynda G. Albright-Borough Manager,

Denise L. Clare-Secretary

A motion was made by Dave Fink and seconded by Stan Dietrich to accept the minutes of the last meeting.

ROLL CALL: Ayes- Smith, Fink, Dietrich, Blefgen

Nayes- None

VISITORS

None

The Trustee Treasurer’s, Administrative Treasurer’s and Sewer B,R, & I reports were reviewed.

ACCT. # Account Name Bal.-Jan. 07 Credits Debits Bal.-Feb. 07

1576025802 Water-1995 Settlement Fund $ 0.00 $ 0.00

1576025820 Water-1995 Revenue Fund $ 0.00 $ 0.00

1576025839 Water-1995 Debt Service $ 78,170.37 $ 313.55 $ 78,483.92

1576025848 Water-1995 Debt Ser. Res. Fund $245,918.03 $ 986.42 $246,904.45

1576025857 Water-1995 B, R, & I $660,117.00 $ 2,648.69 $662,765.69

1576025866 Water-1995 Rebate Fund $ 0.00 $ 0.00

HAMBURG MUNICIPAL AUTHORITY

OPERATING WATER/SEWER ACCOUNT ACTIVITY

February 1, 2007 to February 28, 2007

Water Revenue Account – Balance on February 1, 2007 $ 370,919.55

Water Sales/Penalties $ 40,760.08

Cert Fees, Constable Fees, Final Fees $ 742.50

Interest $ 1,346.57

Miscellaneous $ 142.39

$ 42,991.54

$ 413,911.09

Less Paid Out $ (31,849.49)

Balance in Treasury – February 28, 2007 $ 382,061.60

__________________________________________________________________________________________________________

 

Wissahickon Water Account – Balance on February 1, 2007 $ 19,835.11

Fire hydrant fees/penalties $ 25,152.01

Interest $ 146.70

$ 25,298.71

$ 45,133.82

Less Paid Out $ ( 0.00)

Balance In Treasury – February 28, 2007 $ 45,133.82

__________________________________________________________________________________________________________

Fire Hydrant Account – Balance on February 1, 2007 $ 174,368.35

Fire hydrant fees/penalties $ 2,272.43

Interest $ 576.58

$ 2,849.01

$ 177,217.36

Less Paid Out $ (1,181.60)

Balance In Treasury – February 28, 2007 $ 176,035.76

__________________________________________________________________________________________________________

Sewer Revenue Account – Balance on February 1, 2007 $ 239,554.36

Sewer Rentals/Penalties $ 98,496.49

WTMA Rentals/Penalties $ 4,685.34

Interest $ 1,219.28

Tilden Township Debt Payment $ 30,924.89

$ 135,326.00

$ 374,880.36

Less Paid Out $ (71,304.46)

Less Transfer to M & T Bank $ (80,336.93)

Balance in Treasury – February 28, 2007 $ 223,238.97

BOROUGH TREASURER

SEWER BR & I ACCOUNT

AUTHORITY MEETING MARCH 21, 2007

 

CHECKING ACCOUNT - BALANCE IN CHECKING 2/1/07 $ 269,442.25

INTEREST $ 711.85

TOTAL RECEIPTS FOR THE MONTH OF FEBRUARY $ 270,154.10

LESS PAID OUT $ (0.00)

BALANCE IN CHECKING 2/28/07 $ 270,154.10

 

Stan Dietrich asked where the fire hydrant money went. Keith Brobst stated that it went for parts. Stan Dietrich stated that it was not on the list of bills. Keith Brobst stated it would have been on last month’s report.

A motion was made by Stan Dietrich and seconded by Steve Blefgen to accept the Trustee Treasurer’s, Administrative Treasurer’s and Sewer B,R, & I reports as written.

ROLL CALL: Ayes- Smith, Fink, Dietrich, Blefgen

Nayes- None

HAMBURG MUNICIPAL AUTHORITY

ENGINEER’S REPORT

March 21, 2007

 

SANITARY SEWER SYSTEM

SEWAGE TREATMENT PLANT ISSUES

The new wastewater treatment plant continues to meet discharge parameters. Systems Design Engineering, Inc., Keith Brobst and plant staff continues to watch the plant carefully to determine corrective action for the difficulties encountered in the past. Indications of upsets continue to occur and we have increased pretreatment review activities to determine possible causes.

Seal problems with the new clarifiers created difficult issues. The stainless steel bands holding the sludge return seals broke allowing a short cycling of sludge from the clarifiers. The seals have been corrected. US. Filter and DESCCO are working on the problem. The broken bands are unusual.

Systems Design Engineering, Inc. is also working with the Solicitor on the EPA issues.

A bid document for repairs of the collection system is progressing.

Bids will be received for the replacement of the comminutor at the Edenburg Pump Station.

WWTP PROJECT

Bids were received for the Wastewater Treatment Plant on February 17, 2005. The Authority at their February 22, 2006 meeting issued the "Intent to Award" to:

General/Mechanical Contract DESCCO Design and Construction, Inc.

Amount of Contract: $5,866,184.00

Change Orders No. 1 $ 7,412.00

$5,873,569.00

 

Electrical Contract J.B. Electric Corp.

Amount of Contract: $983,469.00

Change Order No. 1 $ 2,791.00

$986,260.00

 

HVAC Contract PSI Pumping Solutions

Amount of Contract: $70,900.00

 

Contracts were executed and the "Notice to Proceed" was issued on March 17, 2006 to all contractors. The pre-construction meeting was held on March 16, 2006. Work is

 

progressing very well. The Contractor is maintaining the work site in a clean and safe condition.

 

Work completed this period:

DESCCO did not perform much work outside during this period. Due to the cold weather they used this period to maintain equipment at their shop.

Work in the Control Building continued for both the General and Electrical Contractors.

The tie over into the new clarifiers was completed on Tuesday, January 9, 2007. The new clarifiers are now being used. The oxidation ditch was started on Monday, January 15, 2007. DEP inspected the facilities prior to start-up on Tuesday, January 2, 2007 and again on February 12, 2007.

Applications for Payment

 

DESCCO Design and Construction Application No. 12 (Requisition 251)

Amount $ 34,675.00

Balance on Contract $1,451,939.00

 

J.B. Electric Corp. Application No. 9 (Requisition 252)

Amount $ 66,975.00

Balance on Contract $260,278.55

 

Systems Design Engineering, Inc. has submitted payment applications for the second and final draw on the PennWorks Loan. The Authority has received confirmation of the DCED allocation of the Berks County grant in the amount of $130,000 per year for 10 years ($1,300,000 total). Documentation is being processed for submittal to Berks County for the $130,000 payment.

 

PUMP STATION PROJECT

 

Bids were received for the Pine Street Pump Station on December 16, 2005. The Authority has issued the "Intent to Award" to:

 

General/Mechanical Contract Pikeland Construction, Inc

Amount of Contract: $585,000.00

Change Orders $ 7,914.00

$592,914.00

 

Electrical Contract Pagoda Electrical, Inc.

Amount of Contract: $206,000.00

Change Orders $ 2,339.72

$208,339.72

 

The Award and Notice to Proceed was issued on January 20, 2006.

Work this period included:

The project is substantially complete. Punch list items are being completed. Project

closeout is in progress.

The first air release port was added to the pumps. It continues to work and the staff ordered 2 additional air release valves for installation.

Applications for Payment

 

Pikeland Construction, Inc.

Amount $ 0.00

Balance on Contract $ 7,500.00

 

Pagoda Electrical

Amount $ 0.00

Balance on Contract $ 0.00

 

WISSAHICKON WATER (no change)

Wissahickon started production. Systems Design Engineering, Inc. and Keith inspected the facility and have instructed Wissahickon on procedures and some operational details.

PROJECTS

 

Bids for the force main upgrade of the Edenburg Pump Station was received September 6, 2006. Intent to award, Award and Notice to Proceed was given at the September 6, 2006 meeting.

The force main installation is complete with exception of the repaving. The final tie-in was completed on December 26, 2006. The pressure on the force main decreased as planned which increased the flow rate from the existing pumps. Pressures and amperage readings are being monitored to determine if the impellers have to be trimmed. No change since last meeting, awaiting final restoration in spring.

WATER SYSTEM

 

WATER PRODUCTION

 

The impoundment dam is full. The filter plant continues to be shut down due to difficulties with operation. All the water for this report period was produced from the wells. Bids were received for replacement of the control system of the filter plant. The contracts have been completed and executed since the last meeting to expedite the project. A design meeting with plant staff was held February 21, 2007.

The project is progressing on schedule.

DOWNTOWN HAMBURG FIRE

The recent fire in downtown Hamburg (Fourth Street) created a low pressure situation in numerous sections of the distribution system. Although many rumors spread about loss of water pressure, broken mains or no water, the system performed as expected. Loss of water pressure at the higher elevations during an extended heavy fir draw is expected with the pipe sizing of the water distribution system. Well 5 was used to regain pressures within the system with a manual start.

Due to the loss of pressure at the higher elevations, a boil water advisory was issued in consultation with the Pennsylvania Department of Environmental Protection. Two tests performed 24 hours apart were clear of all bacteria and the advisory was lifted.

REQUISITIONS

 

Requisition 251 DESCCO Design and Construction $34,675.00

Requisition 252 J.B. Electric Corp. $66,975.00

Requisition 253 Systems Design Engineering, Inc. $13,058.97

Requisition 254 Video Pipe Services $26,388.05

Requisition 314 Systems Design Engineering, Inc. $ 927.56

 

 

Greg Unger reported that the yard work will be done at the WWTP when it is dryer outside and then the job will be done.

At this time, Greg Unger opened the bids for the comminutor for the Edenburg Pump Station. The engineer’s estimate is $40,000-$50,000.

Johnston Construction Co. $53,305.00

Pikeland Construction, Inc. $67,000.00

The McElwee Group $67,200.00

4-M Construction Services Co. $52,950.00

Eastern Environmental Contractors, Inc. $43,930.00

Destine Company, LLC $53,100.00

Heisey Mechanical, Ltd. $38,650.00

A motion was made by Steve Blefgen and seconded by Dave Fink to give the Intent to Award and Notice to Proceed based on reviews by the engineer and solicitor.

ROLL CALL: Ayes- Smith, Fink, Dietrich, Blefgen

Nayes- None

Greg Unger reported that the system worked as expected during the recent fire in the downtown district. Keith Brobst stated that he has a call into the fire chief about this.

Dave Fink stated that the Authority needs to address the radon levels at Well 5. Greg Unger stated that a ventilator needs to me included. Keith Brobst will add an exhaust fan for when the system runs.

Dave Fink reported that the mag meter pit (vault) is getting water in it. Greg Unger stated that this is a historic problem. Greg Unger will have a recommendation to present at the next meeting.

SOLICITOR’S REPORT

Charles (Chip) Haws was in attendance in the absence of Charles Fitzpatrick.

Chip Haws reported that the EPA fine is still at $51,000 but 40% was to go towards a project to improve the system. EPA has rejected the proposals the Authority submitted. There is now a new judge on the case. EPA is willing to give payment arrangements and allow 9

months to pay but at 4% interest ($853.00). It was suggested to pay the fine and move on. Lynda Albright suggested using monies from the B,R, & I fund from Leesport Bank. Greg Unger stated that it should be paid out of the sewer use fund.

A motion was made by Steve Blefgen and seconded by Dave Fink to approve the execution of consent agreement subject to payment plan language being removed from the final order in the amount of $51,000.

ROLL CALL: Ayes- Smith, Fink, Dietrich, Blefgen

Nayes- None

BOROUGH MANAGER’S REPORT

Lynda Albright reported that Cheryl Haas from Tilden Township had an audit and questions the payments from Tilden Township to the Authority. Greg Unger stated that this should be done automatically and that Tilden Township should not have to be billed monthly. They should make monthly payments per the schedule. The amortization schedule money should go to the bank.

Lynda Albright reported receiving a letter from Penn Dot requesting a recommendation for Dutchland Construction. Greg Unger will take care of responding.

Lynda Albright received a letter from CAP regarding their summer activities. Their annual event is to be held July 6-15. They are aware of the gate locking they are required to do. This is an annual event and is allowed to be done.

GOALS-They will be having an event on June 9 and August 5 at Pulpit Rock. A hold harmless agreement has been received for the June 9 event. The August event is a memorial race. The whole area of the AT cannot be used for this purpose. Lynda Albright will notify GOALS of this. They may have their events as scheduled.

A group of Boy Scouts will be hiking the trail this weekend and have asked permission to bring a grill to use on the parking lot. This may be done.

There is an EDU issue at the American House Hotel. There is 1 EDU for the rooms. There will be less rooms after the renovations however, each room will have its own bathroom. So after everything is complete there will be the bar room, the restaurant and 20 rooms. How should the EDU’s be billed for? It should be based on the 1990 usage like everyone else. Lynda Albright will get the numbers together and meet with Greg Unger and Charles Fitzpatrick.

Villas at Hamburg-Darrin Heckman contacted Solicitor Heidi Masano regarding the improvements agreement. 2 will be needed, one for the Borough and one for the Authority. Ms. Masano told Darrin Heckman that everything could be done on one agreement. Lynda Albright informed Heidi Masano that 2 would be needed. Lynda Albright asked the Authority if they want a separate agreement. Greg Unger stated that it should not be combined and the they are 2 separate entities.

CORRESPONDENCE LIST

CORRESPONDENCE NOTES RECEIVED FROM FEBRUARY 22, 2007 TO MARCH 21, 2007

 

 

 

Received copy of SDE Transmittal letter dated 2/27/07 to Pagoda Electric regarding Certificate of Substantial Completion.

Received copy of SDE Transmittal letter dated 2/27/07 to Pikeland Construction regarding Change Orders No. 3 and 4 and Certificate of Substantial Completion.

Received letter from Civil Air Patrol dated February 1 (received March 1) advising of their search and rescue school.

Received copy of SDE Transmittal letter dated 3/5/07 to Berks County Industrial Development Authority regarding Penn Works Loan Payment Req. 1 and 2.

Received a copy of SDE letter to DEP dated 3/13/07 regarding DEP Rules and Regulations Chapter 94 Report for 2006.

Received letter from PennDOT dated 3/14/07 requesting a reference for Dutchland, Inc. of Gap, PA.

Received a letter from G.O.A.L.S.A.R.A. dated 3/15/07 requesting use of Pulpit Rock as in the past.

Received copy of a letter from SDE to EPA dated 3/15/07 regarding Pretreatment Annual Report for 2006.

SUPERINTENDENT’S REPORT

Water/Wastewater Superintendent’s Report February 2007

 

Water

The plant remains off line while the control system is being replaced. Tony, Greg, and I met with OCC to finalize the design.

The cold snap we experienced caused a few problems. We had several "no water" complaints that turned out to be frozen pipes. We also had a few main leaks but considering how bitterly cold it was, we came through pretty well.

During the early month snowstorm there were two incidents where the sprinklers at Exide leaked. While the amount of water used wasn’t enough to cause problems, isolating them from the main also puts other customers out of service. The Authority is taking steps to remedy this issue.

Wastewater

Construction slowed during February. The contractor took advantage of the cold weather to service equipment. They are back at it and working on the indoor renovations.

While we are experiencing some "growing pains", operations are going well. Total chlorine levels are fluctuating for no apparent reason and we will report on violation. We may have torn seals in the secondary clarifiers and will be emptying them shortly for inspection and repair. Effluent quality has been pretty good and other than the chlorine problem we are meeting permit requirements.

Keith Brobst approached the Authority regarding the purchase of a used bolt and pipe threading machine. The cost would be $1,500. A new one from Grainger runs $5,600.

A motion was made by Steve Blefgen and seconded by Dave Finke to purchase the used threading machine at a cost of $1,500.

ROLL CALL: Ayes- Smith, Fink, Dietrich, Blefgen

Nayes- None

BILLS & REQUISITIONS

Stan Dietrich asked about the Berks Envirotech bill. Is this a monthly thing? Keith Brobst stated that it has nothing to do with the plant. Lynda Albright stated that it is SEO work and it gets reimbursed at the end of the year.

Stan Dietrich asked about the USA Bluebook. Does it get used a lot? Keith Brobst stated that it is on and off but more lately.

A motion was made by Stan Dietrich and seconded by Dave Fink to approve the bills and pay them.

ROLL CALL: Ayes- Smith, Fink, Dietrich, Blefgen

Nayes- None

 

HAMBURG MUNICIPAL AUTHORITY

BILLS TO BE PAID

MARCH 21, 2007

 

AT & T s-monthly phone lease $ 14.55

AT & T w-monthly long distance 60.08

BarleySnyder w-646.27-s-1990.88 2,637.15

BarleySnyder w-339.10-s-530.90 870.00

Berks Envirotech, Inc. s-February permit work 169.87

Berks Products Corp w-supplies 309.57

Borough of Hamburg w-83.86-s-437.46 521.32

DelRosario, Roy C. w-constable fees 104.96

Ehrlich Co. Inc. s-monthly pest service 39.00

Exeter Supply Co., Inc. w-1035.10-s-288.01 1,323.11

Four Star Electronics w-248.00-s-496.00 744.00

Hamburg Municipal Authority s-utility bills 34.52

Hach Company w-chlorine reagent 119.03

Kershner, Mike w-replace lamps at plant 458.00

Lehigh Valley Balances s-calibrate balance & weir 188.00

Liquid Motion Inc. s-sludge disposal 13,050.00

Met-Ed s-utility bills 9,313.17

Mountain View Supply w-122.95-s-31.35 154.30

PA One Call System, Inc. w-6.78-s-6.77 13.55

PPL Gas Utilities s-utility bills 3,559.23

Penn Fuel Propane w-propane 607.53

 

 

Penn Pride, Inc. w-95.08-s-319.32 319.32

Penn State s-2 seminars, 2 employees 780.00

Pickel’s General Hauling w-haul stone for ditches 124.00

Pollu-tech Inc. s-polymer 2,037.00

Reading Eagle Co. s-advertise bids for comm. 228.45

Reider, MJ Associates s-laboratory services 2,732.00

Reider, MJ Associates w-laboratory services 332.00

Rodney Loeb Septic Service s-pump Ridge Lawn wet well 97.50

Systems Design Engineering, Inc. w-603.76-s-3643.70 4,247.46

Thren’s Auto Parts s-supplies 78.62

United Parcel Service s-return charge 13.15

USA Bluebook s-pump head 152.67

Verizon w-116.94-s-247.87 264.81

Wertley Machine Shop s-blower repairs 695.68

Zee Medical Service Company s-restock medical cabinet 25.35

 

TOTAL $46,518.95

 

Bills To Be Paid total water $ 5,413.01

total sewer $ 41,105.94

Bills Paid During The Month

total water $ 24,372.41

total sewer $117,805.85

 

Grand Total For Approval

total water $ 29,785.42

total sewer $158,911.79

$188,697.21

PREPAID INVOICE LIST

 

Brobst, Keith L. s-Norton internet security $ 59.54

HMA-Sewer Transfer s-transfer of revenues 17,255.67

Nalco Co s-polymer 734.70

Met-Ed w-2724.67-s-8230.89 10,955.56

HMA-Sewer Transfer s-transfer of revenue 63,081.26

Clare, David A. w-meter reader 196.30

Miller, Ann M. w-meter reader 177.45

Sonon, Craig A. w-meter reader 122.20 Borough of Hamburg w-1301.29-s-1301.29 2,602.58

Borough of Hamburg w-19723.32-s-27015.32 46,738.64

Postmaster of Hamburg w-127.18-s-127.18 254.36

 

TOTAL $142,178.26

 

Requisition #251 Sewer B,R, & I $34,675.00

DESCCO Design & Construction

WWTP-Contract A

 

Requisition #252 Sewer B,R, & I $66,975.00

J.B. Electric

WWTP-Contract B

Requisition #253 Sewer B,R, & I $13,058.97

Systems Design Engineering, Inc.

WWTP Engineering

Requisition #254 Sewer B,R, & I $26,388.05

Video Pipe Service

WWTP-Contract B

Requisition #314 Water B,R, & I $ 927.56

Systems Design Engineering, Inc.

WFP Control Rebuild

A motion was made by Stan Dietrich and seconded by Steve Blefgen to pay the requisitions as presented.

ROLL CALL: Ayes- Smith, Fink, Dietrich, Blefgen

Nayes- None

A motion was made by Stan Dietrich and seconded by Steve Blefgen to approve reimbursement #4 to the operating fund in the amount of $102,940.27.

ROLL CALL: Ayes- Smith, Fink, Dietrich, Blefgen

Nayes- None

NEW BUSINESS

None

OLD BUSINESS

There being no further business, a motion was made by Steve Blefgen to adjourn the meeting at 8:30 p.m.

Attest:

Denise L. Clare, Recording Secretary