MAY 17, 2006

Home
Up

MINUTES OF THE MAY 17, 2006 MEETING OF THE AUTHORITY

The meeting of the Hamburg Municipal Authority was held this evening at the Hamburg Municipal Center with Chairman Steve Smith presiding. The meeting started at 7:08 p.m.

Members Present - Stephen A. Smith, David A. Fink, Stephen H. Blefgen, Roger G. Kuhns, Judy E. Romig

Members Absent - Stanley E. Dietrich

Also Present – Gregory T. Unger-SDE, Charles F. Fitzpatrick-Solicitor, Lynda G. Albright-Borough Manager (arrived 7:15 p.m.), Keith L. Brobst-

Superintendent, Denise L. Clare-Secretary

A motion was made by Steve Blefgen and seconded by Roger Kuhns to approve the April minutes as written.

ROLL CALL: Ayes- Smith, Fink, Blefgen, Kuhns, Romig

Nayes- None

VISITORS

None

The Trustee Treasurer’s, Administrative Treasurer’s and Sewer B,R, & I reports were reviewed.

ACCT. # Account Name Bal.-Mar.-06 Credits Debits Bal.-Apr.06

1576025802 Water-1995 Settlement Fund $ 0.00 $ 0.00

1576025820 Water-1995 Revenue Fund $ 0.00 $ 0.00

1576025839 Water-1995 Debt Service $ 76,094.66 $111,998.84 $188,093.50

1576025848 Water-1995 Debt Ser. Res. Fund $231,052.72 $ 788.96 ($3,950.43) $227,891.25

1576025857 Water-1995 B, R, & I $693,723.45 $ 2,368.80 ($11,933.07) $684,159.18

1576025866 Water-1995 Rebate Fund $ 0.00 $ 0.00

Hamburg, PA March 16, 2006 7:00 p.m.

HAMBURG MUNICIPAL AUTHORITY

OPERATING WATER/SEWER ACCOUNT ACTIVITY

April 1, 2006 to April 30, 2006

Water Revenue Account – Balance on April 1, 2006 $ 286,592.35

Water Sales/Penalties $ 60,364.20

Cert Fees, Constable Fees, Final Fees $ 847.50

Interest $ 16,831.82

Miscellaneous $ 48.50

$ 78,092.02

$ 364,684.37

Less Paid Out $ (138,580.35)

Balance in Treasury – April 30, 2006 $ 226,104.02

__________________________________________________________________________________________________________

Wissahickon Water Account – Balance on April 1, 2006 $ -

Water Sales/Penalties $ 109.48

Interest $ -

$ 109.48

$ 109.48

Less Paid Out $ ( - )

Balance In Treasury – April 30, 2006 $ 109.48

 

Fire Hydrant Account – Balance on April 1, 2006 $ 150,238.89

Fire hydrant fees/penalties $ 2,052.15

Interest $ 397.18

$ 2,449.33

$ 152,688.22

Less Paid Out $ ( 2,836.00)

Balance In Treasury – April 30, 2006 $ 149,852.22

__________________________________________________________________________________________________________

Sewer Revenue Account – Balance on April 1, 2006 $ 320,060.93

Sewer Rentals/Penalties $ 61,490.82

WTMA Rentals/Penalties $ 24,553.86

Interest $ 1,067.52

Sewer Tap-In Fee $ 3,000.00

Miscellaneous $ 337.50

$ 90,449.70

$ 410,510.63

Less Paid Out $ (52,776.39)

Balance in Treasury – April 30, 2006 $ 357,734.24

BOROUGH TREASURER

SEWER BR & I ACCOUNT

AUTHORITY MEETING MAY 17, 2006

 

CHECKING ACCOUNT - BALANCE IN CHECKING 4/1/06 $ 398,126.91

INTEREST $ 969.24

TOTAL RECEIPTS FOR THE MONTH OF FEBRUARY $ 399,096.15

LESS PAID OUT $ (176,287.40)

SYSTEMS DESIGN ENGINEERING, INC. $ 21,685.40

DESCCO $125,712.00

PIKELAND CONSTRUCTION $ 28,890.00

BALANCE IN CHECKING 4/30/06 $ 222,808.75

 

LYNDA G. ALBRIGHT, BOROUGH MANAGER

 

Roger Kuhns asked what the fire hydrants fees and penalties were. The Secretary explained this.

A motion was made by Dave Fink and seconded by Roger Kuhns to accept the Trustee Treasurer’s, Administrative Treasurer’s and Sewer B,R, & I reports as presented.

ROLL CALL: Ayes- Smith, Fink, Blefgen, Kuhns, Romig

Nayes- None

HAMBURG MUNICIPAL AUTHORITY
ENGINEER’S REPORT
May 17, 2006

 

SANITARY SEWER SYSTEM

SEWAGE TREATMENT PLANT ISSUES

The wastewater treatment plant continues to test our operator skill. pH levels require the addition of control chemicals. The sludge dewatering system continues to be used as required.

WWTP PROJECT

Bids were received for the Wastewater Treatment Plant on February 17, 2005. The Authority at their February 22, 2006 meeting issued the "Intent to Award" to:

General/Mechanical Contract DESCCO Design and Construction, Inc.

Amount of Contract: $5,866,184.00

Electrical Contract J.B. Electric Corp.

Amount of Contract: $983,469.00

HVAC Contract PSI Pumping Solutions

Amount of Contract: $70,900.00

Contracts were executed and the "Notice to Proceed" was issued on March 17, 2006 to all contractors. The pre-construction meeting was held on March 16, 2006. Work is progressing very well.

 

Work completed this period:

Oxidation Ditch excavation completed

Clarifier excavation in progress

Clarifier below slab piping

Clearing of outfall line

Construction of new road in progress

Clearing for garage, sludge and chlorine buildings

Applications for Payment

 

DESCCO Design and Construction Application No. 2 (Requisition 203)

Amount $41,400.00

Balance on Contract $5,699,072.00

Systems Design Engineering, Inc. assists the Solicitor on financing issues as required. The self liquidating debt report was completed and provided to Bond Counsel.

PUMP STATION PROJECT

Bids were received for the Pine Street Pump Station on December 16, 2005. The Authority has issued the "Intent to Award" to:

General/Mechanical Contract Pikeland Construction, Inc

Amount of Contract: $585,000.00

Electrical Contract Pagoda Electrical, Inc.

Amount of Contract: $206,000.00

The Award and Notice to Proceed was issued on January 20, 2006. Work on the wet well suction valves and force main tie-in has been completed. The Electrical Contractor has begun work with the main power feed.

Applications for Payment

Pagoda Electrical Application No. 1 (Requisition 205)

Amount $ 5,400.00

Balance on Contract $200,600.00

CORRECTIVE ACTION PLAN and I/I WORK

Systems Design Engineering, Inc. is continuing dialog with DEP on the Connection Management Plan. DEP Planning contacted Systems Design Engineering, Inc. to ask how the schedule is proceeding and an update on Port Clinton.

WISSAHICKON WATER

Wissahickon started production. Keith and Systems Design Engineering, Inc. are scheduling an inspection to determine discharge parameters.

PROJECTS

The application for the design of the force main upgrade of the Edenburg Pump Station has been submitted to DEP. Information for the proposed force main location is being provided to the Solicitor and Keith. The lines are being marked in the field.

WATER SYSTEM

WATER PRODUCTION

The impoundment dam is currently full. Currently all water production is from surface water. Well 5 is scheduled to begin operation on Monday May 15, 2006 to provide water for Wissahickon’s RO units.

Systems Design Engineering, Inc. continues to work with Plant Personnel on new and proposed regulations that may affect the System in future.

WELL 5

A recent inspection by DEP noted that they want an application filed on the cyclonic separator installed nearly 2-3 years ago. Discussions with DEP have indicated that a minor amendment to the water permit should be filed. Systems Design Engineering, Inc. is progressing with the permit amendment per direction of the Authority.

WATER PROJECTS

Systems Design Engineering, Inc. works with staff on minor operation and maintenance issues as required.

REQUISITIONS

Requisition 203 DESCCO Design and Construction $41,400.00

Requisition 204 Systems Design Engineering, Inc. $23,568.77

Requisition 205 Pagoda Electric $ 5,400.00

Greg Unger reported that the Weidman Subdivision does not have water/sewer and this process is not changing anything.

A motion was made by Judy Romig and seconded by Steve Blefgen to approve the Weidman Subdivision plans as presented and authorize Greg Unger to send letters accordingly.

ROLL CALL: Ayes- Smith, Fink, Blefgen, Kuhns, Romig

Nayes- None

Hamburg Square: Seeking final land development approval for the second parcel to build a bank in the parking lot south of the existing building. This bank will be mostly drive-in customers. Greg Unger stated that the water/sewer should remain private but since there are 2 parcels an easement should be obtained. Greg Unger will send a letter. Greg Unger does not recommend approval of the plans at this time.

Greg Unger reported that the WWTP/PSPS work is progressing well.

Greg Unger showed a force main relocation plan.

Greg Unger handed out the self-liquidating debt report. This includes the sewer budget projected for the next 5 years. The figures are shown with an increase to the current rates. It was discovered that the purchased services projections are incorrect. Lynda Albright asked about how long the Windsor Township debt service will remain in effect. Dave Fink thinks it goes until 2010. This will mean a decrease in revenue. Discussion on sewer rates was held as far as when to increase and by how much. Steve Blefgen suggested increasing the service charge to $65 and the overage rate to $50 for at least 2 years. Greg Unger will do the numbers and get out the information to the Authority members. A line item will be added for I & I for the $75,000/year we need to spend on this.

 

SOLICITOR’S REPORT

Charles Fitzpatrick reported on the bond settlement. The papers have been filed with DCED and the project will go to closing on May 31.

PennWorks loan & grant: Closing cannot be scheduled at this time, there is a hold on the funds. Charles Fitzpatrick will notify the Authority when he knows more.

Charles Fitzpatrick has sent letters to the property owners in Edenburg regarding the

R-O-W. 4 have responded and the letter sent to a property owner who moved will be redone and sent to the new owner. Charles Fitzpatrick stated that the residents were asked to pay $5.00/linear foot towards the new R-O-W. The present R-O-W will be shown to the residents so they can see its location and impact to them.

BOROUGH MANAGER’S REPORT

Lynda Albright stated that Met-Ed is looking for a R-O-W at Well 5. This would be for a new house and pole and will be outside the fenced in area. Keith Brobst and Tony LaScala have no issues with the stake out that has been done.

A motion was made by Steve Blefgen and seconded by Roger Kuhns to allow the R-O-W to Met-Ed as requested.

ROLL CALL: Ayes- Smith, Fink, Blefgen, Kuhns, Romig

Nayes- None

The articles of amendment need to be changed to allow for a 6-member board and for Judy Romig to be able to vote on water and sewer issues. Also adding that a majority is 4 members regardless of how many are in attendance. There will be one representative from Windsor Township and one from Tilden Township.

A motion was made by Steve Blefgen and seconded by Dave Fink to Authorize Charles Fitzpatrick to submit the articles of amendment to Harrisburg to be filed.

ROLL CALL: Ayes- Smith, Fink, Blefgen, Kuhns, Romig

Nayes- None

Lynda Albright asked Charles Fitzpatrick if he spoke to Larry Ernst regarding the deed of dedication for Edenburg Manor II. Charles Fitzpatrick indicated that he actually received the deed several months ago, but had forgotten about it. Lynda Albright then asked if anything was going to be done with the letter received last month from Larry Ernst requesting release from the letter of credit. It was stated that Windsor Township has already submitted their letter of release to Mr. Ernst. Since it is apparent there are manholes that need to be repaired/replaced, the Authority will not send a letter of release or accept the deed of dedication until such time all repairs/replacements have been made in this development.

Lynda Albright asked if access has be gained on any of the outstanding I & I issues. Charles Fitzpatrick stated he is still working on obtaining administrative warrants. Keith Brobst suggested contacting the residents again since it has been a while since the last contact.

SUPERINTENDENT’S REPORT

Water & Wastewater Superintendent’s Report April 2006

Water

Things were looking pretty bleak for surface water for most of the month even though all water for the month came from the dam. We recorded 2 3/4" of rain at the water plant

the weekend of the 21st, which filled the dam nicely. There is still concern about the surface supply and the state has declared a drought watch.

Fire hydrants were flushed with generally good results.

There was a large water main leak on Friday the 20th. A service line blew out of the main on South 4th Street.

This turned out to be a tough weekend when the streaming current monitor started to misbehave Friday evening. Tony got it under control but the next morning it didn’t adjust after a backwash and again needed some attention. It has been fine since then.

The Act 220 Water Withdrawal Report has been submitted to PaDEP as well as a report on our Public Notification Plan.

Wastewater

The general contractor is moving right along on the WWTP but the project at the pumping station is at a standstill while we wait for parts and equipment to arrive.

Video Pipe Services has arrived and started televising and pressure testing the sewer mains. We are working between Pine and Franklin Streets and have found little in the way of leaking joints however we have identified several leaking laterals and house sewers.

On the operations side we are still fighting settling and ph problems. There were 2 minor permit violations during the month, both for low ph.

Keith L. Brobst

Water& Wastewater Superintendent

Keith Brobst stated that readings have been received from Wissahickon and that they have not been operating very long. They are using approximately 35,000 gpd of water and 12,000 gpd of sewer.

Keith Brobst reported that Met-Ed set a new pole at the pump station.

CORRESPONDENCE LIST

CORRESPONDENCE RECEIVED FROM APRIL 19, 2006 TO MAY 17, 2006:

Copy of letter from Atty. Fitzpatrick to Auditor William Gorman dated 4/24/06 relative to the Sewer Revenue Bonds – Series of 2006.

Letter from RBC Capital Market dated 4/24/06 – BOND PURCHASE AGREEMENT

Letter from DEP dated 4/26/06 – Acceptance/Adm. Complete Letter, Application No. 0692406, Amendment 06-1, APS Id No. 20281

Letter from Commonwealth of PA dated 04/28/06 – Funding Adjustment regarding their water use agreement.

Letter from SDE, dated 05/1/06 – Pizza Hut Industrial User Permit Application

Letter from SDE, dated 5/1/06 – Planning Module information for Dale Gassert of Hilltop Garden Center.

Letter of request dated 5/4/06 from US Bank, Stacy Mitchell for a Certificate of Incumbency (per water bond issue of 2001)

Copy of Letter from Atty. Fitzpatrick to DCED relative to the Application for Approval of the Guaranty of $4,230,000 Sewer Revenue Bonds.

Information from SDE dated 5/1/06 which included Cert. Of Self Liquidating Debt and a set of the Edenburg Force Main Properties.

Copies of letters from Atty. Fitzpatrick sent to the Edenburg Force Main Property Owners regarding the right-of-way issue.

Letter sent to Authority from Dept. of Labor and Industry dated 5/12/06 relative to the PENNWORKS grant and use of prevailing wages for project. (Turned over to Solicitor and Engineer for review and response.

BILLS & REQUISITIONS

Roger Kuhns asked about the blocked sewer. Was the blockage caused by a restaurant? Keith Brobst stated that it was not.

Steve Blefgen asked where the heaters were fixed. Keith Brobst stated it was at Ridge Lawn on the starters.

Judy Romig had questions on the phone bills.

A motion was made by Judy Romig and seconded by Roger Kuhns to pay the bills as presented.

ROLL CALL: Ayes- Smith, Fink, Blefgen, Kuhns, Romig

Nayes- None

 

HAMBURG MUNICIPAL AUTHORITY

BILLS TO BE PAID

MAY 17, 2006

AT & T s-monthly phone lease $ 14.55

AT & T w-monthly long distance 83.53

BarleySnyder w-434.30-s-3125.70 3,560.00

Berks Envirotech, Inc. s-April permit work 35.50

Berks-Mont Newspapers, Inc. w-fire hydrant notice 112.80

Blue Mountain Computer Services w-211.98-s-125.00 336.98

Bonkovich, David B. w-240.00-s-360.00 600.00

Borough of Hamburg w-83.91-s-164.16 248.07

Dalious, D. S. Fire Equipment w-77.00-s-269.00 346.00

Del Rosario, Roy C. w-constable fees 87.50

Eastern Environmental Contract s-install seals 2,522.00

Envirodyne Systems Inc. s-bearing assembly 516.80

Exeter Supply Co., Inc. w-parts 918.00

Fuller Equipment Group LLC s-sensor 164.18

Gorman & Associates P.C. w-2500.00-s-2500.00 5,000.00

Grainger s-boots 35.92

Hach Company s-nitrification inhibitor 23.50

Henn’s Garage w-80.10-s-50.40 130.50

Kershner, Mike s-replace heater 180.30

Liquid Motion Inc. s-sludge disposal 2,900.00 Met-Ed w-1499.09-s-7228.08 8,727.17

PA DEP s-storage tanks registration 225.00

PA One Call System, Inc. w-6.80-s-6.80 13.60

PPL Gas Utilities s-monthly utility bill 2,064.78

Penn Fuel Propane w-propane 534.24

Penn Pride, Inc. w-153.84-s-257.42 411.26

Reider, MJ Associates w-laboratory services 340.00

Reider, MJ Associates s-laboratory services 160.00

Rentschler, Randall Inc. s-open blocked sewer 310.00

Rentschler, Randall Inc. s-plumbing supplies 151.50

Systems Design Engineering, Inc. w-393.91-s-2415.87 2,809.78

Univar USA Inc. s-supplies 2,932.87

Verizon w-109.21-s-237.52 346.73

Waste Management of SE PA s-sludge disposal 1,269.50

Werley, Francis L. Inc. s-oil 167.50

TOTAL $38,280.06

Bills To Be Paid total water $ 7,866.21

total sewer $30,413.85

Bills Paid During The Month

total water $132,392.39

total sewer $ 25,829.83

Grand Total For Approval

total water $140,258.60

total sewer $ 56,243.68

$196,502.28

PREPAID INVOICE LIST

Wachovia Bank w-loan payment $111,739.01

Sonon, Craig A. w-meter reader 191.75

Clare, David A. w-meter reader 182.65

Miller, Ann M. w-meter reader 163.80

Koletar, Stephen H. w-constable fees 50.00

Borough of Hamburg w-19915.48-s-25678.98 45,594.46

Petty Cash w-18.35-s-19.50 37.85 Postmaster of Hamburg w-131.35-s-131.35 262.70

 

TOTAL $158,222.22

Requisition #203 Sewer B,R, & I $23,568.77

Dessco

WWTP Upgrade

Requisition #204 Sewer B,R, & I $23,568.77

Systems Design Engineering

WWTP Improvements

Requisition #205 Sewer B,R, & I $5,400.00

Pagoda Electric

PSPS Electric Contract

A motion was made by Steve Blefgen and seconded by Dave Fink to approve the requisitions as presented.

ROLL CALL: Ayes- Smith, Fink, Blefgen, Kuhns, Romig

Nayes- None

NEW BUSINESS

None

OLD BUSINESS

Roger Kuhns asked about second meters for outside use.

There being no further business, a motion was made by Roger Kuhns and seconded by Judy Romig to adjourn the meeting at 9:04 p.m.

Attest:

Denise L. Clare, Recording Secretary